Removal and disposal of wharf decking comprised of 5,800 m² of 150 mm thick reinforced concrete on top of 200 mm thick laminated creosote-treated timber piles.
Removal and disposal of 1,390 lineal metres of creosote-treated timber pile caps and 735 creosote-treated timber support piles. Approximately 95% of pile caps and 60% of creosote-treated timber piles were recycled.
Demolition and disposal of reinforced concrete wharf abutment and twin slab foundations. Final quantity of concrete removed was approximately 4,200 metric tonnes.
Foreshore excavation followed by slope and scour protection using imported aggregate materials to achieve a finished “natural beach” look.
Project was completed one month ahead of schedule.